Work on Pueblo Levee Wrapping Up for the Season

Work on the Arkansas River levee that protects downtown Pueblo from flooding is winding down for the season. Planning for the next phase is underway.

Removing and replacing the concrete facing from more than a half mile of the original structure should begin in early November.

Project engineer Kim Kock says they’ll stop when they reach the kayak course near the 4th Street Bridge because that will allow extra time, “to look for ways to improve recreational opportunities along the river and adjacent to the kayak course.”

The current work will be completed as budgeted. Initial cost estimates for the next phase are around $3 million and two more phases are anticipated.

Also, local artists are working with the contractor to move the concrete panel with the corn maiden mural to the El Pueblo Museum.

Listen at KRCC.org

This entry was posted in KRCC, Reported Story and tagged , , . Bookmark the permalink.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s